Estimated Start Date
June 20, 2023
Estimated End Date
December 31, 2025
Address
Silver Start Mountain located at 9885 Silver Star Rd, Vernon, BC
Budget
$155,000
Funding Source
Community Works Funds
Participating Community
Area C
Status
Completed
Project Description
The Silver Star Firehall Upgrades project involves replacing the aging cedar siding on the firehall, which is over 35 years old and in poor condition. A 2024 condition assessment identified the need for immediate replacement. Additionally, the cedar siding poses a significant fire hazard due to the firehall's location in an extreme wildfire risk area. The project will improve the building’s durability and safety by installing non-combustible or fire-resistant siding. The roof and exterior siding needed to be replaced. The siding will be replaced with metal siding to ensure the building is FireSmart compliant.
Image

Timeline
Target Completion Date
Complete
No
Department Contact